Project Implementation Mechanism

After signing the contract and approving the project, the following steps are taken:

  1. The site engineer prepares the site facilities as follows:

    1. Administrative offices and their office equipment.
    2. Construction of project protection walls.
    3. Installation of project signage.
  2. The survey engineer prepares the survey work for the project dimensions using specialized equipment and delivers the information to the technical office.

  3. The technical office prepares the executive plans for the first phase items and obtains approval from the consultant.

  4. The technical office prepares the time schedules and quantity schedules according to the project’s overall program.

  5. The site engineer carries out excavation work after receiving the approved plans from the consultant.

  6. The site engineer monitors the work for the items according to the time schedules prepared by the technical office.

  7. The site engineer submits weekly and monthly reports to the project manager.

  8. The site engineer and the quality control monitor the project work.

  9. The site engineer and the technical office approve the materials from the consultant according to the material supply schedules.

  10. The site engineer, with the technical office, prepares the abstracts for approval from the consultant.